Yıldırım Beyazıt Market Place Solar Power Plant 682 kWe / 720 kWp
27 September 2024

Süre :
Unit / Directorate : Directorate of Research and Development
Start Date : 01 April 2016
End Date : 01 July 2016

Production Start Date: 01 July 2016


YILDIRIM BEYAZIT MARKET PLACE 04/2016 The installation started on 07/2016 and the installation process was completed and production started.

In our facility where it was installed 3000 solar panels were used. An average annual electricity production of 948 MWh is expected in our facility.

With the clean energy produced, an average of 23700 trees were saved annually and approximately 521 tons of CO₂ emissions. is blocked. In addition, clean energy is produced to meet the electricity needs of 189 households annually.